UK airports prepare for November runway and taxiway works

November will bring a fresh round of runway maintenance and airfield works at several major UK airports, with overnight closures and taxiway restrictions set to change how some of the country’s busiest airports operate.
For aviation enthusiasts, the notices offer an early look at where runway availability will be reduced, which airports will switch to single-runway operations and where taxiway layouts will be affected during the winter maintenance period.
At Glasgow Airport, Runway 05/23 will be available strictly by prior permission during scheduled overnight periods from 1 to 20 November. The restriction applies Sunday to Thursday between 23:00 and 06:00 UTC, with works in progress cited in NOTAM I7423/26. This is a restriction on runway availability rather than confirmation of a full airport closure.
Manchester Airport is also scheduled to carry out overnight maintenance on Runway 1 from 1 to 5 November, between 22:30 and 06:00 local time. Runway 2 is expected to remain in use as the sole runway during these periods. The dates include weather contingency and spare nights, meaning the work may not be required every night.
Birmingham Airport faces a longer programme of winter runway maintenance, with planned night closures beginning on 2 November and continuing into early December. The published schedule includes closures from 23:30 to 06:00 UTC on specified nights, with the airport’s runway unavailable during the closure periods.
Bristol Airport will have a different arrangement. Planned full aerodrome closures are scheduled five nights a week, Sunday to Thursday, from 8 November to 4 December. The closures will run from 23:30 to 05:45 UTC and are intended to support essential runway and airfield maintenance. During those periods, the airport will not be available for diversions under its published Plan 39 arrangements.
Taxiway works will also continue at Heathrow, where several restrictions extend into November and December. Taxiway Link 35 is closed, while the runway 09L/27R entry and exit points at taxiways AB11 and A11 are also restricted. Taxiway A North is closed between taxiways C and E, affecting part of the airport’s extensive ground-movement network.
At Birmingham, published notices also cover metal plates on taxiways Delta and Echo. These are localised taxiway restrictions rather than runway closures, but they form part of the wider programme of airfield works taking place around the network.
Edinburgh Airport has further infrastructure work on its airfield, including Taxiway Foxtrot fillet works and the continuing closure of Stand 26. These restrictions are separate from a full runway closure and illustrate how maintenance can affect aircraft parking and ground movements without stopping normal runway operations.
The works highlight the different approaches airports take to maintaining infrastructure during the quieter overnight hours. Some, such as Manchester, can keep operating using a second runway, while others schedule periods when the aerodrome itself is unavailable.
The published notices provide the current planned dates, but maintenance schedules can change if work is completed early or conditions prevent it from going ahead.







Comments