Heathrow third runway now targeted for 2039 as expansion costs rise

Heathrow Airport’s proposed third runway is now expected to become operational in 2039, four years later than the Government’s original 2035 ambition, as fresh details emerge about the cost of progressing the airport’s expansion plans.
The revised timeline reflects the scale of the planning, regulatory and infrastructure work still required before construction can begin. Heathrow has maintained that it is aiming to secure planning permission by 2029, with the runway capable of opening within a decade of that approval.
The airport has previously acknowledged that 2035 was an ambitious target. During evidence to the House of Commons Transport Committee in October, Heathrow executives confirmed that 2039 was a more robust delivery scenario under the conditions currently facing the project.
The timing is not the only challenge facing the expansion programme.
On 25 November, the Civil Aviation Authority (CAA) published a new consultation examining how further early development costs associated with Heathrow expansion should be treated through airport charges.
Heathrow Airport Limited has told the regulator it expects to incur up to £304 million in expansion-related costs during the first half of 2027. The expenditure is intended to maintain the option of submitting a Development Consent Order application by the end of next year.
The consultation also includes costs forecast by Heathrow West Limited, which is progressing an alternative expansion proposal. The company expects expenditure of approximately £46 million during 2026 and a further £35 million in the first half of 2027.
If the CAA’s proposed arrangements are implemented, the total amount of early expansion costs eligible for recovery across the relevant periods could reach approximately £700 million.
The regulator estimates that recovering these costs over 20 years could equate to around 60p to 70p per passenger journey at Heathrow. This would be in addition to existing airport charges, although the final amount will depend on the regulator’s decisions and the costs ultimately approved.
The CAA has stressed that the proposed figures are ceilings rather than automatic payments. Expenditure will remain subject to further scrutiny, including checks that costs are justified, efficient and do not involve unnecessary duplication.
The consultation is open for responses until 12 January 2027. The CAA expects to publish a further consultation next spring, with a final decision currently anticipated in summer 2027.
Heathrow’s expansion remains a major infrastructure proposal for the UK aviation industry. The airport’s wider plans include a new runway, additional terminal capacity and significant changes to surrounding infrastructure, including the M25.
However, there is still no live planning application for the third runway, and the project must progress through the relevant planning and regulatory processes before construction can move forward.
For airlines and passengers, the combination of a longer delivery timeline and further development expenditure raises important questions about the future cost and timing of expansion at the UK’s busiest airport.
The third runway remains a long-term ambition, but with an opening now targeted for 2039 and hundreds of millions of pounds in further early costs under consideration, the programme still has significant hurdles to overcome.